The organic fertilizer granule coating machine is a key equipment at the end of the production line, and its installation quality and the atomization state of the oil spraying system directly determine the anti crushing and appearance of the finished fertilizer. In the years of equipment manufacturing experience at Jinglong Agriculture, we are well aware that only by installing the equipment firmly and adjusting the fuel injection parameters properly can we ensure uniform adhesion of protective film on the particle surface and reduce subsequent transportation losses. This article focuses on the actual implementation process of the device, from basic verification to optimization of atomization parameters, providing a set of operable technical solutions to help frontline technicians successfully complete debugging tasks.
Equipment foundation inspection and positioning installation
In the initial stage of installation, site flatness is the primary consideration factor. According to GB 5083-1999 "General Principles for Safety and Health Design of Production Equipment", the horizontal deviation of the equipment base should be controlled within the allowable range to avoid additional vibration during operation. Jinglong Agriculture suggests that operators first clean up the debris on the foundation, lay a cement base, and reserve anchor bolt holes. After the equipment is in place, a level should be used to detect the height difference of the four corners of the body, ensuring that the error is less than 2 millimeters. Then tighten the anchor bolts using a diagonal cross method to prevent uneven force from causing deformation of the frame. For large-scale coating machines, it is also necessary to connect the power supply and gas interface, confirm that the grounding resistance meets safety regulations, and ensure the electrical safety of operators.
At this stage, if ground subsidence or loose bolts are found, secondary grouting reinforcement should be carried out in a timely manner. Especially in areas with high vibration, it is recommended to use a shock-absorbing cushion layer. This is not only for the consideration of equipment lifespan, but also to maintain the stability of the subsequent spraying process.
Requirements for connection of fuel injection system pipelines
The fuel injection system is the core component of the coating machine, responsible for delivering anti caking agents or protective liquids to the inside of the drum. Pipeline connections must follow the principle of tightness to prevent liquid leakage from causing waste or environmental pollution. Before connection, all joints should be cleaned to remove oil stains and impurities. **Use chemically resistant stainless steel pipes and secure them with sealing rings to ensure no leakage. The installation position of the oil pump should be as close as possible to the storage tank, shorten the length of the oil suction pipeline, and reduce the risk of air resistance.
In pipeline layout, sharp bends and dead points should be avoided to ensure smooth fluid flow. For operations in high-temperature environments, it is necessary to install insulation protective covers on the outside of the oil pipes. In addition, the connection point between the pressure gauge and the flow meter should be selected in a pipe section that is easy to observe and has less vibration, making it convenient for daily reading recording. If aging cracks are found in the pipeline, it should be replaced immediately and cannot be operated with defects.